Re: I'm using kplato 0.6.2, but it doesn't schedule tasks
Dag Andersen <[email protected]> Wed, 12 Sep 2007 11:53:28 +0200
| Newsgroups | gmane.comp.kde.kplato |
|---|---|
| Message-ID | <[email protected]> |
Onsdag 12 september 2007 02:21 skrev Sam Roberts: > "Resource leveling. Resources are just allocated to the requested task > even when allready booked to other task(s). The resulting conflict must > be resolved manually by adding task links or constraints to avoid > parallel scheduling of the tasks" Yeahh, kplato is still 0.x revision so it's not "feature complete" > > Which makes it not so useful for me :-( Also, I can't figure out how to > to "task links". In the gantt chart you press LMB over one task and drag the pointer tothe other task. When have defined a link (select View->TaskLinks to see them) you can double click the link to edit it. > > I've been asked to produce GANTT charts for my project, and I'll be > damned if I'm using windows to do it... > > Should I try to build from source? Or am I just too early? You are a bit early for serious work :( > > Also, I noticed on the website comments about merging with taskjuggler, > should I just use taskjuggler? You can certainly use taskjuggler, it's more mature than kplato. > > Sam > > _______________________________________________ > kplato mailing list > [email protected] > https://mail.kde.org/mailman/listinfo/kplato -- Mvh Dag Andersen