Re: some first thought on kplato 0.6.94
Dag Andersen <[email protected]> Fri, 30 May 2008 12:19:42 +0200
| Newsgroups | gmane.comp.kde.kplato |
|---|---|
| Message-ID | <[email protected]> |
S=F8ndag 25 maj 2008 12:18 skrev mimoune djouallah: > >> can we assign cost to resources instead of tasks. > > > > You specify cost for resources in the columns "Normal Rate" and "Overti= me > > Rate" (the last isn't quite implemented yet). > > > >> thanks > > is there any plan to assign cost of a resources to a particular > account, instead of assigning cost account to activities, it is a > very useful feature, as we tend to make financial analysis of the > project based on the cost of resources ( materials and people ). No, I don't have any plans for that. Could you add it as a wish to http://bugs.kde.org/ > > i know i am just moaning, > this project need more man power not complaints. = I think so, too ;) > > friendly yours > > > Mvh > > Dag Andersen > > _______________________________________________ > > kplato mailing list > > [email protected] > > https://mail.kde.org/mailman/listinfo/kplato > > _______________________________________________ > kplato mailing list > [email protected] > https://mail.kde.org/mailman/listinfo/kplato -- = Mvh Dag Andersen