Re: Earned Value terminology (was RE: Managing Extreme Programming)

"Dale Emery <[email protected]>" <[email protected]>
Newsgroups gmane.comp.programming.extreme-programming.adoption
Message-ID <[email protected]>
Hi Laurent,

> > [>] Yep and that the "gap" for XP, since velocity describes a
> > "level of effort" (in terms of EV) in which effort expended is the
> > same as "value." 
> 
> From what I understand, the mapping is rather simple - if you expand 
> the acronym BCWP as "budgeted cost of work performed" you get almost 
> the word-for-word definition of velocity, i.e. the total effort that 
> a given feature had been estimated to require.

That's close.  BCWP is the number of points associated with some set
of completed stories.  It's only when you divide it by some unit of
time that you get velocity.

Dale



------------------------ Yahoo! Groups Sponsor ---------------------~-->
Turn flat surfaces into speakers with the Soundbug.
http://us.click.yahoo.com/QWAVSC/onCFAA/xGHJAA/nhFolB/TM
---------------------------------------------------------------------~->

To unsubscribe from this group, send an email to:
[email protected]

 

Your use of Yahoo! Groups is subject to http://docs.yahoo.com/info/terms/
lmpx.com only provides a reader for public news (NNTP) servers. It is not affiliated with the servers or forums shown here and is not responsible for the content of articles, which is written by their respective authors.