Re: Managing Extreme Programming

"Dale Emery <[email protected]>" <[email protected]>
Newsgroups gmane.comp.programming.extreme-programming.adoption
Message-ID <[email protected]>
Hi Glen,

> > In George's example, y is the Budgeted Cost of Work Performed
> > (BCWP), and z is the Actual Cost of Work Performed (ACWP).  So
> > George's cost-per-velocity-unit is ACWP/BCWP, the reciprocal of
> > Cost Performance Index (CPI).  If you can dollarize CPI, you can
> > dollarize velocity.
>
> Yep and what's missing is BCWS.

Does allocating stories to iterations give you BCWS?  If not, what
more is needed to produce BCWS?

Dale



------------------------ Yahoo! Groups Sponsor ---------------------~-->
Turn flat surfaces into speakers with the Soundbug.
http://us.click.yahoo.com/QWAVSC/onCFAA/xGHJAA/nhFolB/TM
---------------------------------------------------------------------~->

To unsubscribe from this group, send an email to:
[email protected]

 

Your use of Yahoo! Groups is subject to http://docs.yahoo.com/info/terms/
lmpx.com only provides a reader for public news (NNTP) servers. It is not affiliated with the servers or forums shown here and is not responsible for the content of articles, which is written by their respective authors.