Re: When a sprint has been canceled...
| Newsgroups | gmane.comp.programming.scrum.general |
|---|---|
| Message-ID | <[email protected]> |
If the team canceled the sprint there would be nothing to Review (Demo) correct? It’s all lost, reverted in the source control. However it is VERY important to do the Retro. Many teams will need to vent, (see grieving process) - and the org. may want to look at why they changed direction outside the typical sprint boundaries. Was it a reaction or an opportunity? > On Jul 30, 2015, at 5:56 AM, [email protected] [SCRUMDEVELOPMENT] <[email protected]> wrote: > > Hi, > > I'm wondering what ceremonies have still to take place once a sprint has been canceled and Scrum Guide has very little guidance on this. > > Should Spint Review and/or Sprint Retrospective still take place and how soon? > > > > Thanks in advance > > >