Thanks Ron.
Are these teams that start out with very small items to begin with? (Sort of like micro-stories pattern -- most stories 3 days or less?)
-------Charles Bradley
Chief Executive Officer
Professional Scrum Trainer
http://AgileSoftwareTraining.com
Agile Software - Training, Consulting, Coaching
From: "Ron Jeffries [email protected] [SCRUMDEVELOPMENT]" <[email protected]>
To: [email protected]
Sent: Tuesday, November 24, 2015 12:45 PM
Subject: Re: [SCRUMDEVELOPMENT] Decomposing only minimal work in Sprint Planning
#yiv1695890846 #yiv1695890846 -- #yiv1695890846 .yiv1695890846ygrp-photo-title{clear:both;font-size:smaller;height:15px;overflow:hidden;text-align:center;width:75px;}#yiv1695890846 div.yiv1695890846ygrp-photo{background-position:center;background-repeat:no-repeat;background-color:white;border:1px solid black;height:62px;width:62px;}#yiv1695890846 div.yiv1695890846photo-title a, #yiv1695890846 div.yiv1695890846photo-title a:active, #yiv1695890846 div.yiv1695890846photo-title a:hover, #yiv1695890846 div.yiv1695890846photo-title a:visited {text-decoration:none;}#yiv1695890846 div.yiv1695890846attach-table div.yiv1695890846attach-row {clear:both;}#yiv1695890846 div.yiv1695890846attach-table div.yiv1695890846attach-row div {float:left;}#yiv1695890846 p {clear:both;padding:15px 0 3px 0;overflow:hidden;}#yiv1695890846 div.yiv1695890846ygrp-file {width:30px;}#yiv1695890846 div.yiv1695890846attach-table div.yiv1695890846attach-row div div a {text-decoration:none;}#yiv1695890846 div.yiv1695890846attach-table div.yiv1695890846attach-row div div span {font-weight:normal;}#yiv1695890846 div.yiv1695890846ygrp-file-title {font-weight:bold;}#yiv1695890846 #yiv1695890846
Charles,
On Nov 24, 2015, at 2:09 PM, Charles Bradley - Professional Scrum Trainer and Coach [email protected] [SCRUMDEVELOPMENT] <[email protected]> wrote:
Have any of you run across real life teams that decompose only the first couple of days worth of work in Sprint Planning? If so, in what contexts did you find this beneficial? Also, what was the team's main reason(s) for doing it this way?
I’ve encountered teams that don’t really decompose at all, instead just talking about how they’ll likely do things.
The advantages of decomposing little include: less work; fewer mistakes; less commitment to a plan made at the worst possible moment; more chance for the team to swarm; more emphasis on what’s most important i.e. first.
Ron Jeffriesronjeffries.comDon't ignore your dreams; don't work too much; say what you think; cultivate friendships; be happy. -- Paul Graham