Re: Re: Big Stories

"Michael Wollin [email protected] [SCRUMDEVELOPMENT]" <[email protected]> Wed, 25 Nov 2015 06:46:25 -0800
Newsgroups gmane.comp.programming.scrum.general
Message-ID <[email protected]>
One of the underlying problems in my view is that the team is small and underpowered. So a story like compare two information sources (10 fields) and display/highlight any differences is too big. So get and display the 10 fields from A is one story, get and display the 10 fields from B is another story, and compare and display the discrepancies is the third story. 

Most teams I know could do the whole thing in a day or two. This one will take two weeks each. I want them to discover for themselves the issue. (It was exacerbated by the holiday.) 

They are new and just forming as well. Being a cross functional team is novel to this department. Being empowered to ask for what they need may also be new. 


------------------------------------
Posted by: Michael Wollin <[email protected]>
------------------------------------