MRP Date reference = 999999 ?
"Jim Kerr" <JKerr-FaIC0pVkSM6w7v2zf2itdNJR4SXAr38/@public.gmane.org>
| Newsgroups | gmane.comp.systems.as400.jbausers |
|---|---|
| Organization | Gleason Corporation |
| Message-ID | <005001c81a78$6ac8c780$3201a8c0@DBQ2M441> |
When I review the MRP demand (also referred to as MRP Inquiry, program MR050) I see supply records displayed as 99/99. The MRP supply file MRP73 does contain a value of 9999999 in field MRPD73 for certain work orders. Does anybody have an explanation as why the date would be 9999999 ? Thanks in advance. Jim Kerr _______________________________________________ This is the System 21 Users (SYSTEM21) mailing list To post a message email: SYSTEM21-Zwy7GipZuJhWk0Htik3J/[email protected] To subscribe, unsubscribe, or change list options, visit: http://lists.midrange.com/mailman/listinfo/system21 or email: SYSTEM21-request-Zwy7GipZuJhWk0Htik3J/[email protected] Before posting, please take a moment to review the archives at http://archive.midrange.com/system21.