Re: Available to Promise
"Kevin Fox" <[email protected]>
| Newsgroups | gmane.comp.systems.as400.mapics |
|---|---|
| Organization | Kevin Fox |
| Message-ID | <[email protected]> |
I think this is getting closer. Here are the formulas from the book: (COM - Available to Promise) Demand: The total customer backlog and manufacturing allocations due each day. It can also include generated demand from MRP/MPSP, if requested. Expected receipts/Supply: Total expected receipts each day including open, firm planned, and planned orders. Period ending inventory (PEI): Beginning balance plus supply minus demand for each day. Required starting inventory (RSI): Demand minus supply plus the future unmet demand (FUD). This is the amount of inventory needed to meet a specific days demand plus any shortage in coverage against future demand. The calculation for RSI for a day is demand minus supply plus FUD. The RSI a day is the FUD of previous day. Future unmet demand (FUD): The amount of demand that is not covered by supply in future days. For a specific day, FUD is the RSI of the next day Available to promise (ATP): Projected ending inventory (PEI) minus the future unmet demand (FUD) for each day. When I make this a simple formula I get. Demand = Pick Requirements + IA + AL + Firm PLN, PLN Supply = Open MO, Open PO, Firm MO, PO Req, FIRM PO, planned MO + Planned PO PEI = First Date = On Hand + Supply - Demand PEI = Next Days = Previous PEI + Supply - Demand RSI = Demand - Supply + FUD or RSI = previous days FUD FUD = next day's RSI ATP = PEI - FUD As you can see from the description, RSI = today - 1 + FUD = today + 1 +RSI **THUS RSI = FUD = RSI.... Here is my problem. ATP is returning results that are unusable. For example, an item shows negative ATP for the entire MRP horizon because I have demand 2 years from now for which I have not released a PO. If the demand is beyond the CMLT time fence, why would ATP not say...available. For example: Suppose an item has 0 on hand, 0 demand, 0 supply, 0 atp and 0 unmet future demand. And a lead time of 60 days. I now get a customer order for 100 units due 75 days from today, well beyond CMLT. Why does ATP show -100 available and not OK if it is beyond CMLT? Kevin mobile (909) 762-1384 -----Original Message----- From: mapics-l-bounces-Zwy7GipZuJhWk0Htik3J/[email protected] [mailto:mapics-l-bounces-Zwy7GipZuJhWk0Htik3J/[email protected]] On Behalf Of Jeff Snyder Sent: Tuesday, May 18, 2010 11:23 AM To: mapics midrange Subject: Re: [MAPICS-L] Available to Promise Something to the effect by date: Onhand - demand (customer, Allocations, or peg to demand) - Unmet future demand + scheduled receipt (either MO PO, or planned order). Unmet demand is aggregated up until the next scheduled receipt. Hope this helps Jeff > From: [email protected] > To: mapics-l-Zwy7GipZuJhWk0Htik3J/[email protected] > Date: Tue, 18 May 2010 13:41:19 -0400 > Subject: Re: [MAPICS-L] Available to Promise > > Check the PDF documentation for IM. May have the same info. > > > Best regards, Dick > > Richard (Dick) Stover > Consulting Manager > Guide Technologies LLC > (c) 215-499-8530 > [email protected] > > > -----Original Message----- > From: mapics-l-bounces-Zwy7GipZuJhWk0Htik3J/[email protected] [mailto:mapics-l-bounces-Zwy7GipZuJhWk0Htik3J/[email protected]] > On Behalf Of Kevin Fox > Sent: Tuesday, May 18, 2010 11:39 AM > To: 'MAPICS ERP System Discussion' > Subject: [MAPICS-L] Available to Promise > > All > > > > We seem to be having a problem with the Available To Promise. Does anyone > have the calculation formulas? There used to be an excel sheet on infor365, > but the link is broke. > > > > > > Kevin > > mobile (909) 762-1384 > > > > _______________________________________________ > This is the MAPICS ERP System Discussion (MAPICS-L) mailing list > To post a message email: MAPICS-L-Zwy7GipZuJhWk0Htik3J/[email protected] > To subscribe, unsubscribe, or change list options, > visit: http://lists.midrange.com/mailman/listinfo/mapics-l > or email: MAPICS-L-request-Zwy7GipZuJhWk0Htik3J/[email protected] > Before posting, please take a moment to review the archives > at http://archive.midrange.com/mapics-l. > > _______________________________________________ > This is the MAPICS ERP System Discussion (MAPICS-L) mailing list > To post a message email: MAPICS-L-Zwy7GipZuJhWk0Htik3J/[email protected] > To subscribe, unsubscribe, or change list options, > visit: http://lists.midrange.com/mailman/listinfo/mapics-l > or email: MAPICS-L-request-Zwy7GipZuJhWk0Htik3J/[email protected] > Before posting, please take a moment to review the archives > at http://archive.midrange.com/mapics-l. > _______________________________________________ This is the MAPICS ERP System Discussion (MAPICS-L) mailing list To post a message email: MAPICS-L-Zwy7GipZuJhWk0Htik3J/[email protected] To subscribe, unsubscribe, or change list options, visit: http://lists.midrange.com/mailman/listinfo/mapics-l or email: MAPICS-L-request-Zwy7GipZuJhWk0Htik3J/[email protected] Before posting, please take a moment to review the archives at http://archive.midrange.com/mapics-l. _______________________________________________ This is the MAPICS ERP System Discussion (MAPICS-L) mailing list To post a message email: MAPICS-L-Zwy7GipZuJhWk0Htik3J/[email protected] To subscribe, unsubscribe, or change list options, visit: http://lists.midrange.com/mailman/listinfo/mapics-l or email: MAPICS-L-request-Zwy7GipZuJhWk0Htik3J/[email protected] Before posting, please take a moment to review the archives at http://archive.midrange.com/mapics-l.