Re: Lead time calculation
"Dave Turbide" <[email protected]>
| Newsgroups | gmane.comp.systems.as400.mapics |
|---|---|
| Message-ID | <[email protected]> |
The short answer is: it doesn't. MRP looks at the lead time code and picks up the appropriate lead time for the (planned) item: M = manufacturing lead time; P = purchasing lead time. There is no calculation from the components or from the routing. These are manually maintained fields for the item. Dave Turbide, CFPIM, CIRM, CSCP, CMfgE Production Solutions (603) 964-6903 www.daveturbide.com - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - message: 1 date: Tue, 12 Feb 2013 16:17:13 -0800 from: Jayakrishnan P V <[email protected]> subject: [MAPICS-L] (no subject) All, Can someone help me to find out how MRP derive parent item lead time, start order date, from component items lead time? -- Thanks Jayakrishnan -- This is the MAPICS ERP System Discussion (MAPICS-L) mailing list To post a message email: MAPICS-L-Zwy7GipZuJhWk0Htik3J/[email protected] To subscribe, unsubscribe, or change list options, visit: http://lists.midrange.com/mailman/listinfo/mapics-l or email: MAPICS-L-request-Zwy7GipZuJhWk0Htik3J/[email protected] Before posting, please take a moment to review the archives at http://archive.midrange.com/mapics-l.