Re: MRP/VPi in a Seasonal Business
"Dave Turbide" <[email protected]>
| Newsgroups | gmane.comp.systems.as400.mapics |
|---|---|
| Message-ID | <[email protected]> |
With MRP, it's difficult to handle seasonality that exceeds capacity. Since MRP is an infinite planner, it will simply net available inventory against the forecast and generate an un-achievable schedule. The obvious 'fix' is to spread the forecast out to level the load but as soon as you build the extra inventory, the system will net it out against future forecasts and reduce the production plan going forward. You have to 'hide' the inventory, by putting it in another warehouse, for example. In MPSP, you can directly enter / manipulate the master schedule, essentially short-circuiting this netting logic. You tell it what to build and when and that's what it will do. This is also an infinite scheduler so it won't spread the load for you based on capacity limits. You spread the work by spreading the master schedule. message: 1 date: Fri, 7 Jun 2013 11:57:06 -0500 from: "Marc Rohde" <[email protected]> subject: [MAPICS-L] MRP/VPi in a Seasonal Business When you have seasonality that outpaces your capacity what are some of the best approaches to ensuring that MRP/VPi will recommend an appropriate start date for production based on the forecasted demand? We want to build up to a peak of the season and then let inventory diminish after the peak. Dave Turbide, CFPIM, CIRM, CSCP, CMfgE Production Solutions (603) 964-6903 www.daveturbide.com -- This is the MAPICS ERP System Discussion (MAPICS-L) mailing list To post a message email: MAPICS-L-Zwy7GipZuJhWk0Htik3J/[email protected] To subscribe, unsubscribe, or change list options, visit: http://lists.midrange.com/mailman/listinfo/mapics-l or email: MAPICS-L-request-Zwy7GipZuJhWk0Htik3J/[email protected] Before posting, please take a moment to review the archives at http://archive.midrange.com/mapics-l.