Re: Including Handling Allowances in MRP which is a fixed quantity, not a percentage
Kevin Fox <[email protected]>
| Newsgroups | gmane.comp.systems.as400.mapics |
|---|---|
| Message-ID | <CALo5ePdK7ZuG+WVQOtrbYnjrmfKt-yrj6nStPxB45TrEFyFQsw@mail.gmail.com> |
Alan Easiest non-modification method is to do two things: 1. Ensure that Standard Lot Size (NOT Standard Batch size) is set to the most common lot size produced for the item. If this cannot be determined, you should not be using MRP. 2. Then use Yield value at the operations in the routing that consume the 'fixed' quantities, but you have to enter as a % of the standard lot size. The result will automatically plan for the consumption of items scrapped during the destructive testing in setting up the operations. Example: Supposed that the standard lot size is 100, and there are 4 operations. Operation 2 consumes 2 units and Operation 3 consumes 5 units. This means that the net yield is 93% Assuming I start with enough material to produce 100, but only get 93 as a result of losing 7 unites (2 + 5) in the process. At operation 2 the yield is 98% (100-2= 98 units) At operation 3 the yield is 95% (98-5=93 93/98=5%) The system will no plan for and recommend ordering enough material to ensure the net result for the order will be 100. So assuming that the item required 100 pieces to produce 100 pieces, with the yield it would be adjusted to require 107 unites to produce 100 pieces. Your Pick List requirements will be 107. Your net expected, quantity to stock will be 100. MRP will plan accordingly based on demand. Not if the demand is greater or less than the standard batch size, the material requirements will be adjusted accordingly and will adhere to the rules used in the Order Policy Code. Your costs will be adjusted to reflect the additional material required as well. Note: I used a simple example to keep the math simple. In the real world, the standard lot sizes are rarely 100, and the yields are rarely only 2 operations. Don't get caught up onto trying to over complicate. For example, I've seen companies try to play with the standard lost size to try and 'fine' tune it. Remember, if you consume more or less of the material than the standard lot size adjusted by the yield factors, the next MRP run will adjust for the overage or under use of the material. Kevin Fox On Thu, Feb 25, 2016 at 10:44 PM, Alan McKenzie <[email protected]> wrote: > Hi, > > Our industry seems to have a particular requirement. > > In the cable manufacturing process, each steps consumes a fixed quantity > of the manufactured product in the start-up of the manufacturing cycle. > This excess demand must be included in the planned quantity as it cascades > down the indented Bill of Material. The issue is that this fixed quantity > per manufactured item, must somehow be added at each level in the BOM to > ensure sufficient component quantity is manufactured to cover all the > Allowance requirements in the levels above. Please note that this is a > fixed quantity and can not be a percentage. > > In an example provided quickly in a recent discussion, it was determined > that there can be up to an 8% scrap quantity produced by these allowances > over the complete production processes. This is currently being handled > manually by the planners. > > I have anticipated including the Allowance on the Item Warehouse, and > adding it to planned quantities during the MRP cycle. I'm not sure exactly > how and where to add the allowances. There are 3 User Exits in the > planning run which I suspect could be used. Where this is added depends on > when the projected planned quantities are initially created. > > If you have any ideas, or would like more information, please contact me > through this facility. > > Rgrds, > > Alan > XA Consultant > [cid:[email protected]] > Registration Number: 1967/005978/07 > Office: +27 12 381 1405 | Switchboard: +27 12 381 1400 > Mobile: +27 (0) 82 453 7990 > E-mail: AMcKenzie-JmGRM1/[email protected] > > -- > This is the MAPICS ERP System Discussion (MAPICS-L) mailing list > To post a message email: MAPICS-L-Zwy7GipZuJhWk0Htik3J/[email protected] > To subscribe, unsubscribe, or change list options, > visit: http://lists.midrange.com/mailman/listinfo/mapics-l > or email: MAPICS-L-request-Zwy7GipZuJhWk0Htik3J/[email protected] > Before posting, please take a moment to review the archives > at http://archive.midrange.com/mapics-l. > > -- This is the MAPICS ERP System Discussion (MAPICS-L) mailing list To post a message email: MAPICS-L-Zwy7GipZuJhWk0Htik3J/[email protected] To subscribe, unsubscribe, or change list options, visit: http://lists.midrange.com/mailman/listinfo/mapics-l or email: MAPICS-L-request-Zwy7GipZuJhWk0Htik3J/[email protected] Before posting, please take a moment to review the archives at http://archive.midrange.com/mapics-l.