2.00 release plans

Hugh Daniel <[email protected]> Tue, 18 Feb 2003 19:02:46 -0800
Newsgroups gmane.network.freeswan.devel
Message-ID <[email protected]>
-----BEGIN PGP SIGNED MESSAGE-----

 We have some firm plans on 2.00's public release and we might as
well release them to the world, and if your reading this list your the
world and here are the plans:

Feb. 20

  Feb. 20th, We cut an 2.00-rc1, it _will_ have warts that have to be
fixed in following releases, so we get to suffer from .0 release
disease just like every one else.  Tough, we 'freeze' Thursday.

  The freeze conditions are that doc is NOT frozen and that everything
else is, WARTS and all unless we find a 'failure' class bug.  So there
are two days to get in what needs to be, and it dam well better be
minor.

  Note that if you have a patch or a dream that needs some structure
to be different in the 2.00 series, time's up.  Maybe if it's small
enough we can accommodate you, maybe, and remember that 3.00 is not
far off (2.00 is ment to be just a 'delivery' and not a 'development'
platform).

  As project lead MCR is working on a list of things that will be
changed before the freeze, there are a few known at this point.  We
will try to produce a -pre8 tonight (look for it on the FTP server)
that is obviously very very close to what -rc1 will be.


Feb. 28

  Two big things happen February 28th.  We intend to put out a 2.00
(final) that should be perfectly usable, but will have known warts.
To deal with the warts and the like we will add a "Weather Report" as
has been discussed before to the www.freeswan.org web page, this will
give folks a paragraph description of the known state of current
releases.

  Do note that these 'Weather Reports' will mostly _lag_ the release
more then precede it.

  The other thing that happens on that Friday is that the daily
snapshot on that Friday should have the first version of "co-terminal"
SA's, thus a machine can have both WAVEsec _&_ OE running at the same
time.  This is only a first pass, we will see from that what needs do
be done to make it working and polished.


Mar. 07

  We intend to release 2.01-pre1, with a target of a working
co-terminal setup and every wart needed for FreeS/WAN use at IETF and
beyond fixed.

  After this work will stop for about two weeks for a DNSsec workshop
and IETF, after that we will consider a schedule for 2.01, likely in
the second half of April.


  Please remember that our small team can't do everything everyone
wants, not even what _we_ want to get done.  This is a big and
complex problem space and we are serious trying to do what no one else
seems even willing to contemplate, make most machines secure most of
the time.

  Thus if there is something that you would like have have working in
FreeS/WAN, please at least test that something in the next 9 days.

		||ugh Daniel
		[email protected]

			Systems Testing & Project mis-Management
			The Linux FreeS/WAN Project
			http://www.freeswan.org

-----BEGIN PGP SIGNATURE-----
Version: 2.6.3ia
Charset: noconv
Comment: For the matching public key, finger the Reply-To: address.

iQCVAwUBPlLz01ZpdJR7FBQRAQFygAQArn+MV18uoYxnAvlZ8MODUlwUEXlm3WLG
Pz1EKi7tDfYOLoFDwMz34YvNBroyx/is7fc1FTxM6sOm4bq8GEgUkW83d4LGUxTa
MvtroaLHwRagpiDBZIO+OTx0BmIqKPNxNUuLI0TcApHT/FWb35OP1vDMkf/cG4oj
salN8Xio6Y8=
=9a23
-----END PGP SIGNATURE-----