agenda for 1-24 site plan meeting
Felix Kersting <[email protected]> Tue, 23 Jan 2007 23:06:04 -0800
| Newsgroups | gmane.org.clubs.gobiodiesel.mixmasters |
|---|---|
| Message-ID | <[email protected]> |
Friends - here is the agenda for tonight's meeting (1/24/07, 7 - 8:30 pm
on-site) See you there!
Agenda for 1/24/07 site plan meeting
I have left spaces for other ideas and will update this document as minutes.
We will discuss;
1. where we are
a. waste oil receiver in place
b. one oil heater in place & wired
c. one water heater in place & wired
d. one processor plumbed - need to install vent
e. 2 processors insulated
f. settling tote in place
g. one wash tote in place
h. dryer under cover
i. .
j. .
k. .
l. .
m. .
2. what it takes to get back on track making fuel
a. test the processor – fix any leaks
b. be able to heat 65 gal oil at one time or do small batches
i. settle in the processor for now or get proper valve on settling tote
c. sprinkler heads in wash tote and test on real fuel
d. .
e. .
f. .
g. .
h. .
i. .
3. what are the next steps after fuel restart
a. pipe 2^nd processor - put gasket in lid - install vent
b. more oil heating or set up timers – power drop
c. .
d. .
e. .
f. .
4. where do we go from there
a. hard pipe dryer PVC should be ok
b. 2^nd settling tote needs to nest on first one
c. 2^nd wash tote needs to nest on first one
d. hard pipe wash totes (pvc)
e. get more water heaters
f. more containment for water heaters or use conex
g. Hard pipe the entire process (steel)
h. .
i. .
j. .
k. .
l.
5. processor turnover to the mixmasters for full production (probably a little premature but let's be thinking about it)
6. process tweaks to meet the 3/27 test
7. rewrite the Brew Book to accommodate processor changes and process changes
I hope we can plan another month's worth of site work, with the goal of
resuming limited fuel production this weekend or next. Washing and
drying will follow on the weekend following fuel production restart.
Other tasks –
Clean up the site. As we consolidate the waste oil, follow the code
based site plan –
1. Need to submit for C of O to City of Milwaukee,
2. get fuel/WVO containment dwg approved
3. build fuel WVO containment
4. build methanol containment