Re: Digital Realty- Non Renewal
Shane Ronan via NANOG <[email protected]>
| Newsgroups | gmane.org.operators.nanog |
|---|---|
| Message-ID | <CAJ_LqoErg6RZGF0gM9_pm59=nwRtAOKKUD_ecAavkN=nhuS3JQ@mail.gmail.com> |
We've long surpassed the power available from the commercial power grid. MANY large scale data centers are using cogeneration with natural gas turbines. I don't however think they would be approved for that in the middle of downtown Chicago. shane On Thu, Apr 23, 2026 at 6:54 PM Matthew Petach via NANOG < [email protected]> wrote: > On Thu, Apr 23, 2026 at 3:36 PM Christopher Morrow via NANOG < > [email protected]> wrote: > > > On Thu, Apr 23, 2026 at 5:32 PM Mike Hammett via NANOG > > <[email protected]> wrote: > > > > > but Cermak is a big building. They can't use up *THAT* much of it. > Also, > > diversifying to tier 2 markets would probably help a lot not have so many > > eggs in one basket. > > > > how much power, exactly, is landing in Cermak? do you think you could > > use all of that up with your set of 120kw NVidia racks? > > > > What, nobody is putting shipping-container-sized micro nuclear reactors on > the rooftops of the buildings to augment power capacity? > > Come on, people, start thinking outside the box a little. ;) > > Matt > > (yes, yes, permitting, upgrading electrical wiring to handle 10MW coming in > from a shipping container on the roof, not as trivial as it sounds...but > still, I think we're coming up on the tail end of counting entirely on the > power grid to deliver power to high-density compute facilities) > _______________________________________________ > NANOG mailing list > > https://lists.nanog.org/archives/list/[email protected]/message/KHRBBKCQ7GM5VPVMYJSJUGQJNHNERDD2/ _______________________________________________ NANOG mailing list https://lists.nanog.org/archives/list/[email protected]/message/TFTAO6ZZPFAVSWF6WIRVAXUAF5SNUIYG/