[Axis2] 1.4 Release Management / Planning

Davanum Srinivas <[email protected]>
Newsgroups gmane.text.xml.axis.devel,gmane.text.xml.commons.devel
Message-ID <[email protected]>
-----BEGIN PGP SIGNED MESSAGE-----
Hash: SHA1

Team,
How about we cut a Axis2 1.4 RC1 end of next week (14th) to get things started? We can do one RC a week or so.

Rich,
You taking on Axiom. Right?

Jeremy,
Can we please plan for some woden milestones? Please let us know.

Ajith,
You taking on XmlSchema. Right? Please let us know.

Sanka,
Can you please help with Neethi as usual? Please let us know.

Deepal,
Would you have time for Axis2? I can volunteer as Release Manager if you wish or we can share the responsibility as
usual. Either works for me.

Sandakith,
Stand alone TCK would be the biggest blocker for the final release. Any feedback on how that's going?

thanks,
dims


-----BEGIN PGP SIGNATURE-----
Version: GnuPG v1.4.5 (Cygwin)

iD8DBQFH0AnTgNg6eWEDv1kRAu47AJ9Gj1bxKIgAg09Feu87yVdMyqqSuwCghtq5
2LbRF6CxY6bl7NguRASVk/c=
=ijFU
-----END PGP SIGNATURE-----
lmpx.com only provides a reader for public news (NNTP) servers. It is not affiliated with the servers or forums shown here and is not responsible for the content of articles, which is written by their respective authors.