Re: start date of task
Richard Hult <[email protected]>
| Newsgroups | gmane.comp.gnome.apps.mr-project.user |
|---|---|
| Message-ID | <1034930628.2510.15.camel@sliff> |
tis 2002-10-15 klockan 17.51 skrev Jérôme Bouat: > How to define the start date of a task ? You could use the task view and set a "must start on" constraint on the task by clicking the start cell, selecting the right constraint type, and then choose your start date. Or, if you simply want to set the start date of the first task, you probably just want to set the start date of the project, which is done in the project properties dialog (which you can find in the File menu). Or, if you just want to make sure one task is put after another, you should create a dependency from the first task to the second. You do this in the Gantt view, by clicking on the first task and dragging to the second. Hope it helps, Richard -- Richard Hult [email protected] CodeFactory AB http://www.codefactory.se/