tor 2003-01-16 klockan 22.05 skrev Aivo Kalu:
> >> This is implemented feature? I didn't find it from 0.8pre at least. 
> >
> >In the task view, as opposed to the gantt view... clicking the start
> >cell of a task in the table should pop up a calendar with a few
> >constraint options.
> 
> Now I see it. Thats good,  now I think there are no problems to use the
> program for my work. Anyway, possibility to drag the task in Gantt view
> would be quicker :)

Yeah, we've been discussing exactly how to do it... when you drag a
task, it could automatically set a start-no-later-than constraint, and
also mark the task as such somehow. Or we could make it only do that if
you hold Control or Shift or something, to make it less easy to set
constraints by mistake. 

-- 