Re: A first impressions with using MrProject
Benjamin BAYART <[email protected]> Thu, 16 Jan 2003 22:24:48 +0100
| Newsgroups | gmane.comp.gnome.apps.mr-project.user |
|---|---|
| Message-ID | <[email protected]> |
Le Thu, Jan 16, 2003 at 07:06:47PM +0200, Aivo Kalu: > > 3. Perhaps should there be a quicker way to assign a ressource to the task ? > Not via task properties, but instead right from the pup-up menu ? I was thinking of a solution that can be of interest: what about a list of resources, say on the right side of the gantt chart, where you can drag a resource from, and drop it on a task. I don't know if it's easy to do, but it sounds like rather easy to use. Another good point can be to highlight the tasks assigned to a resource when the resource is selected. By the way, as this would give a rather large window at the end, this part should be removable (or reduced). Benjamin.