Re: Work beyond working hours
Mikael Hallendal <[email protected]> 26 Feb 2003 13:12:04 +0100
| Newsgroups | gmane.comp.gnome.apps.mr-project.user |
|---|---|
| Organization | CodeFactory AB |
| Message-ID | <[email protected]> |
ons 2003-02-19 klockan 20.36 skrev Andres Montiel: Hi! > Is it possible to set a task to go beyond the working hours? I try to > pull the bar to the non-working hours and it just bounces back. If you have a resource assigned to the task you can change the calendar of that resource so that he works on weekends or just override that particular weekend. Regards, Mikael Hallendal -- Mikael Hallendal [email protected] CodeFactory AB http://www.codefactory.se/ Cell: +46 (0)709 718 918