ons 2003-02-19 klockan 20.36 skrev Andres Montiel:

Hi!

> Is it possible to set a task to go beyond the working hours? I try to
> pull the bar to the non-working hours and it just bounces back.

If you have a resource assigned to the task you can change the calendar
of that resource so that he works on weekends or just override that
particular weekend.

Regards,
  Mikael Hallendal
-- 