Project Leveling
Jay Gindin <[email protected]> 10 Apr 2003 09:25:19 -0700
| Newsgroups | gmane.comp.gnome.apps.mr-project.user |
|---|---|
| Message-ID | <[email protected]> |
I know that MrProject is not yet 1.0, so I apologize in advance if this question is premature... I've read the available docs, but can't find an answer to this... I have a number of tasks, all of which are going to be worked on by the same person (resource), yet few of them have any relationships. Using MS Project (please forgive me...it's the only other project planning software I've used), I can have it "level" the project so that the one person is only working on one task at a time. Is this possible with the current version of MrProject? If not, how have others worked around this problem? I'd rather not create artificial relationships between tasks... thanks, jay ---------------- Jay R. Gindin "Though copious errors guarantee worthlessness, zero errors says nothing about the value of the software." -- Source unknown