Re: Project Leveling
Benjamin BAYART <[email protected]> Thu, 10 Apr 2003 23:18:01 +0200
| Newsgroups | gmane.comp.gnome.apps.mr-project.user |
|---|---|
| Message-ID | <[email protected]> |
Le Thu, Apr 10, 2003 at 09:25:19AM -0700, Jay Gindin: > > Is this possible with the current version of MrProject? If not, how have > others worked around this problem? I'd rather not create artificial > relationships between tasks... I tried several approach to this: 1. Create artificial relationships 2. Change by hand the start date of a given task (which is, in fact, what MSProject does automatically) 3. Use a dedicated plugin which is in the CVS repository but not in the usual distribution (have to be activated) and which might conflict with recent developpements. I don't like the first one, it creates artificial stuff. I don't like the third one: I prefere to choose which task have to be done first. So I would suggest the second one is not so bad... Regards, Benjamin.