Re: Resource overutilization

Jiri <[email protected]> 21 Apr 2003 21:17:27 +0200
Newsgroups gmane.comp.gnome.apps.mr-project.user
Message-ID <1050952647.2482.37.camel@man9>
Hi,

I agree with you that some function to resolve resource
conflicts using the existing task priority would be very useful.
It's a lot of work to change all later tasks manually if you have to
replan an early task.

To allow overlapping of tasks you can just assign a resource 
to less than 100%. Ok, it's not so fancy as your proposal with
an automated adaption of time commitment, but also less complexity.

Jiri


On Mon, 2003-04-21 at 01:55, Sasan Iman wrote:
> After some thinking I think a more complete solution to over-utilization
> would be:
> 
> 1-Add a property to each task (can be overlapped, cannot be overlapped).
> 2-If task cannot be overlapped, use the "priority" property to schedule
> it with respect to other tasks using the same resource, use any-order
> for tasks with same priority.
> 3-For tasks with SAME PRIORITY that can be overlapped, extend the
> duration of the tasks so that the total time spent on the task by
> resource adds up to his full time commitment.
> example: tasks A and B (each taking one day) should both be done by
> resource R, If tasks A and B are overlap-able, then show the duration as
> two days for each.
> In this context, overlap-able tasks with same priority form a
> "super-task" that can be scheduled using its priority with respect to
> other non-overlap-able tasks for the same resource.  
> 
> Thanks for reading my comments and I look forward to your feedback. 
> 
> Sasan