Re: Resource overutilization
Jiri <[email protected]> 21 Apr 2003 21:17:27 +0200
| Newsgroups | gmane.comp.gnome.apps.mr-project.user |
|---|---|
| Message-ID | <1050952647.2482.37.camel@man9> |
Hi, I agree with you that some function to resolve resource conflicts using the existing task priority would be very useful. It's a lot of work to change all later tasks manually if you have to replan an early task. To allow overlapping of tasks you can just assign a resource to less than 100%. Ok, it's not so fancy as your proposal with an automated adaption of time commitment, but also less complexity. Jiri On Mon, 2003-04-21 at 01:55, Sasan Iman wrote: > After some thinking I think a more complete solution to over-utilization > would be: > > 1-Add a property to each task (can be overlapped, cannot be overlapped). > 2-If task cannot be overlapped, use the "priority" property to schedule > it with respect to other tasks using the same resource, use any-order > for tasks with same priority. > 3-For tasks with SAME PRIORITY that can be overlapped, extend the > duration of the tasks so that the total time spent on the task by > resource adds up to his full time commitment. > example: tasks A and B (each taking one day) should both be done by > resource R, If tasks A and B are overlap-able, then show the duration as > two days for each. > In this context, overlap-able tasks with same priority form a > "super-task" that can be scheduled using its priority with respect to > other non-overlap-able tasks for the same resource. > > Thanks for reading my comments and I look forward to your feedback. > > Sasan > _______________________________________________ > MrProject mailing list > [email protected] > http://lists.codefactory.se/cgi-bin/mailman/listinfo/mrproject