Re: Resource overutilization
Sasan Iman <[email protected]> Mon, 21 Apr 2003 14:15:42 -0700
| Newsgroups | gmane.comp.gnome.apps.mr-project.user |
|---|---|
| Message-ID | <[email protected]> |
I don't think assigning to less than 100% would solve the problem. If I have to manually identify the overlapped time, then I can schedule it manually as well. The goal is to remove the necessity to manually identify the overlapped time (region of over-utilization) and also remove the need to rework the schedule because of changes in earlier parts. Even if I did manually assign less than 100%, then when schedule changes, I still need to go back and modify the percentages again. Not very convenient. Do you guys think my proposal is practical to implement? Am I missing some requirement in my suggested solution? Thanks. Sasan On Mon, 2003-04-21 at 12:17, Jiri wrote: > Hi, > > I agree with you that some function to resolve resource > conflicts using the existing task priority would be very useful. > It's a lot of work to change all later tasks manually if you have to > replan an early task. > > To allow overlapping of tasks you can just assign a resource > to less than 100%. Ok, it's not so fancy as your proposal with > an automated adaption of time commitment, but also less complexity. > > Jiri > > > On Mon, 2003-04-21 at 01:55, Sasan Iman wrote: > > After some thinking I think a more complete solution to over-utilization > > would be: > > > > 1-Add a property to each task (can be overlapped, cannot be overlapped). > > 2-If task cannot be overlapped, use the "priority" property to schedule > > it with respect to other tasks using the same resource, use any-order > > for tasks with same priority. > > 3-For tasks with SAME PRIORITY that can be overlapped, extend the > > duration of the tasks so that the total time spent on the task by > > resource adds up to his full time commitment. > > example: tasks A and B (each taking one day) should both be done by > > resource R, If tasks A and B are overlap-able, then show the duration as > > two days for each. > > In this context, overlap-able tasks with same priority form a > > "super-task" that can be scheduled using its priority with respect to > > other non-overlap-able tasks for the same resource. > > > > Thanks for reading my comments and I look forward to your feedback. > > > > Sasan > > _______________________________________________ > > MrProject mailing list > > [email protected] > > http://lists.codefactory.se/cgi-bin/mailman/listinfo/mrproject