Re: 'Work'-field for tasks keep increasing...

Benjamin BAYART <[email protected]> Wed, 23 Apr 2003 11:21:37 +0200
Newsgroups gmane.comp.gnome.apps.mr-project.user
Message-ID <[email protected]>
Le Wed, Apr 23, 2003 at 11:11:49AM +0200, Allan Beaufour:
> 
> > I tried to use you working time, and got funny stuff but not the one
> > you describe:
> 
> I usually use the Gatt diagram, and the work just keeps increasing if I
> doubleclick the Work-field...

I do not see the same bug here. Which version are you using? I'm using
a recent CVS snapshot, so something like a "pre 0.10". Maybe this bug
have been already fixed...

> > It should perhaps be reported as a bug...
> 
> It is a bug. No matter what definition one chooses as a working day, it
> should not keep increasing :)

That clearly is a bug, but I didn't see the same behaviour here.

Do you have a test file you can send me that have this behaviour, and
that I can test here... If I see the same trouble, I'll try to find the
bug and to propose a patch to the development team.

Regards,

	Benjamin.