Re: 'Work'-field for tasks keep increasing...

Richard Hult <[email protected]> 23 Apr 2003 11:15:46 +0200
Newsgroups gmane.comp.gnome.apps.mr-project.user
Organization CodeFactory AB
Message-ID <[email protected]>
ons 2003-04-23 klockan 11.02 skrev Benjamin BAYART:
> Le Tue, Apr 22, 2003 at 11:04:39PM +0200, Allan Beaufour Larsen:
> > 
> > I have just created a new project, and it seems to work fine except for
> > one thing: Every time I enter a value in a work-field it gets increased
> > when I leave it. That is: If I enter '2d 9t' it ends up being '3d', and
> > '3d' ends up being '3d 1t'. It also increases if I doubleclick the field
> > (or print). Weird, and extremely annoying...
> > 
> > It seems like the error is provoked by the fact that I changed the hours
> > of a working day. I changed the working days to go from '9:00-12:00' and
> > '12:40-20:00'. If I change them back, it works fine. Do you by any
> > chance have some (hidden) expectations for how long a working day is?
> 
> For what I've seen in the sources, there are a lot of places where there
> are suppositions that a working day is 8 hours. At least in several
> places in the gantt stuff.
> 
> It shouldn't be that hard to fix, but there are a lot of places where to
> check everything is ok.
> 
> And there a few places where it's verry hard to handle: suppose a case
> where there are different kind of working days (full day, morning only,
> afternoon only), which one is the "basic" day to be used when one is
> displaying the amount of work for a task?
> 
> For what I've seen, if you say "1d" in the "work" cell, it's handled as
> "8 hours". Just because one need to handle a convenient way to decide
> this point. And, in a case like yours, in one day of duration there can
> be more than one day of work. So, keep in mind: work and duration are
> not equal for you.
> 
> I tried to use you working time, and got funny stuff but not the one
> you describe:
> - when I write "1d" in the task tree (gantt or tasks view), it's handled
>   as a full work-day (as defined in the calendar)
> - it displays "1d" in the task tree
> - then I edit the task, and it displays "1.3" in the "work" field
> - if I change it to be "1", close, re-edit, it comes back to 1.3, still
>   1d in the task tree.
> - if I change to "8h" in the task tree, in the edit dialog it's
>   displayed as "1.0".
> 
> So, there are strange things, but probably only in the graphical part,
> and not really in the calculations. When MrProject reads, it reads
> working days as defined in the calendar, but when it displays in the
> task dialog, it displays in 8-hours working days independantly of the
> calendar.
> 
> It should perhaps be reported as a bug...

In some places we just hardcode a day to be 8 hours for now, which is
clearly wrong. We just need to decide what the definition of "day"
should be. IMO, we should just have one per-project setting for this,
because having day mean different things for different resources (based
on their calendar) will be very confusing. Any ideas/comments on how to
handle this?

Richard

-- 