Re: Modifying start time
Kurt Maute <[email protected]> Tue, 13 May 2003 22:49:07 -0400
| Newsgroups | gmane.comp.gnome.apps.mr-project.user |
|---|---|
| Message-ID | <1052880546.14633.3.camel@Kronk> |
On Mon, 2003-05-12 at 14:31, Kees van den Broek wrote: > Hi, > > I can modify the start date of a task by clicking on the date and using > the calender. The constraint is: must start on. I can choose any day I > like, but once I click OK, all dates before today are discarded. Only > today and dates after today are accepted. Why is this? > I have already done some tasks before today and I still want them in the > task list. I did a quick test, and it looks like you may be trying to set the task start date to a day before the project start date, whose default is today. If you change the project start date first, then it will let you go back earlier. You can do this by choosing Project -> Edit Project Properties. _______________________________________________ MrProject mailing list [email protected] http://lists.codefactory.se/cgi-bin/mailman/listinfo/mrproject