Re: New web site & MrProject 0.6
Richard Hult <[email protected]>
| Newsgroups | gmane.comp.gnome.apps.mr-project.user |
|---|---|
| Message-ID | <1029752792.20072.13.camel@sliff> |
sön 2002-08-18 klockan 19.24 skrev Alvaro: > > I have looked at it. The problem is that the cost is calculated as: > > total_cost += (mrp_task_get_duration (task)/3600) * cost; > > The "cost" for a resource is ok, but the duration for a 1 day task is > 32400, I don't know why. Duration is calendar duration, including weekends etc... I just checked in a fix that uses work instead (not completely right, it should use duration excluding nonworking time, but for now it's working). /Richard -- Richard Hult [email protected] CodeFactory AB http://www.codefactory.se/