Re: New web site & MrProject 0.6

Richard Hult <[email protected]>
Newsgroups gmane.comp.gnome.apps.mr-project.user
Message-ID <1029752792.20072.13.camel@sliff>
sön 2002-08-18 klockan 19.24 skrev Alvaro:
>
> I have looked at it. The problem is that the cost is calculated as:
> 
> total_cost += (mrp_task_get_duration (task)/3600) * cost;
> 
> The "cost" for a resource is ok, but the duration for a 1 day task is
> 32400, I don't know why.

Duration is calendar duration, including weekends etc... I just checked
in a fix that uses work instead (not completely right, it should use
duration excluding nonworking time, but for now it's working).

/Richard

-- 