Re: Feature suggestion: 2 times for "duration of task": optimistic and pessimistic

Kurt Maute <[email protected]>
Newsgroups gmane.comp.gnome.apps.mr-project.user
Message-ID <[email protected]>
Hi All.

I think Edmund raises some good points to keep in mind
as development proceeds.

> To reach a Milestones it takes **one** person to
> take responsibility for the
> timing and resource of this milestone.
> Is has to be **taking** responsibility and not
> **assigned** responsibility
> by the boss.

I agree.  Whenever several resources are assigned to a
task, one should be made "primary".  This primary
resource is the person who agrees to take the
responsibility for achieving the deliverable.

> If the responsibility is assigned, a person can not
> be made responsible if
> failing reaching the milestone.

That depends on what you use for motivation.  ;)

> I suggest that every task is give to durations of
> implementation. The
> optimistic one and the pessimistic one.
> 
> ... For a more
> detailed explanation please
> read “M.Goldrath 1984, The Goal. Excellence in
> Maufacturing”
> 

I agree.  Goldratt's TOC (Theory of Constraints), and
its impact on Project Management is explored more
deeply in "Critical Chain".  In this book, he talks
about targeting a completion date for each task that
is shorter than estimated, and applying that extra
time to a 'Project Buffer'.  Some tasks will be
accomplished by the shortened target date, an others
won't, but the overall effect is to build flexibility
into the plan.

I think there is great opportunity to create some
tools in MrProject that will assist PM's in this area.




=====
Kurt Maute
[email protected]

__________________________________________________
Do You Yahoo!?
HotJobs - Search Thousands of New Jobs
http://www.hotjobs.com
lmpx.com only provides a reader for public news (NNTP) servers. It is not affiliated with the servers or forums shown here and is not responsible for the content of articles, which is written by their respective authors.