Re: Feature suggestion: 2 times for "duration of task": optimistic and pessimistic
Mikael Hallendal <[email protected]>
| Newsgroups | gmane.comp.gnome.apps.mr-project.user |
|---|---|
| Message-ID | <[email protected]> |
tis 2002-08-20 klockan 01.08 skrev Michele Ravani: > On Sun, 18 Aug 2002 21:33:50 +0200 info <[email protected]> wrote: > i> When you change the project plan while implementation, you do loose > i> oversight about > i> what was intended originally, what resources/budget were assigned > i> originally > i> and who changed where and what. > i> So it might be a good idea to have a kind of CVS integrated and be able > i> to show at what time what changed. > > Versioning, together with baselines, could be a rather powerful thing. We where thinking of having support to save several baselines. Would that fill the needs? > A kind of Value at Risk could be computed, saying something like 'there is > a 5% probability that we will overshoot by 30% in time and cost'. > Definitely and interesting idea. With having pessimistic, assumed and optimistic times on each task this shouldn't be a problem to do. Thanks for the input. I would very much appreciate if you could all add things like this in the Bugzilla at (http://bugzilla.codefactory.se) and mark them as "Enhancement". This way we won't loose good suggestions within the mailing list. Regards, Mikael Hallendal -- Mikael Hallendal [email protected] CodeFactory AB http://www.codefactory.se/ Office: +46 (0)8 587 583 05 Cell: +46 (0)709 718 918