Re: Planner-list there is no way to move task in time off ?
Alexandre Franke <[email protected]> Fri, 19 Feb 2010 11:31:07 +0100
| Newsgroups | gmane.comp.gnome.apps.planner.user |
|---|---|
| Message-ID | <[email protected]> |
2010/2/19 Gabriel Rota <[email protected]>: > All task in planner can be planned by hour in work time default 8.00 - > 17.00. > For a day my coworker have planned a server down in time off like 18.30 > to 19.30. > Other day have a normal time. I think I see what you mean now : you would like to have a task happen during non-working days. That can be easily achieved. Here's how: * create a new resource (for instance "Computer") that will work on your task * edit calendar for this resource, maybe create a new calendar * set the days when the work should be done as working days in this calendar * assign tasks to the resource Result: the tasks will be worked on even on weekends. -- Alexandre Franke