Re: Planner-list Digest, Vol 43, Issue 3
Leonardo Perez <[email protected]> Wed, 10 Mar 2010 03:39:50 +0000
| Newsgroups | gmane.comp.gnome.apps.planner.user |
|---|---|
| Message-ID | <[email protected]> |
Thanks Alexander, but let me give an example about my sugestion. Let's suppose a proyect with a number of tasks that sum 18 hours/week of work during 6 months, but, in this proyect I can't to hire personal payed by hours, and I have to hire him part time or full time, (20 hours/week or 40 hours/week of availability). In that case, I'll have to hire the personal part time, and pay the equivalence of 20 hours/week using only 18 hours/week. If I use the value of hour, the real one, the costs of the proyect will be unreal, but if I adjust that cost only for adjust the budget, I won't see the availability of time of the people, unused time. (In this case 2 hours/week). I know that in this example, to identify the overpayed is easy, but in big proyects I could to hire unnecesary extra work. If Planner, let's me choose, the time partition and the pay (500 USD 20hours/week and not only 50 USD/hour), I could to resolve the problem of availability an cost. I hope the question will be clear for everybody. regards, Leonardo Perez > From: [email protected] > Subject: Planner-list Digest, Vol 43, Issue 3 > To: [email protected] > Date: Tue, 9 Mar 2010 12:00:12 +0000 > > Send Planner-list mailing list submissions to > [email protected] > > To subscribe or unsubscribe via the World Wide Web, visit > http://mail.gnome.org/mailman/listinfo/planner-list > or, via email, send a message with subject or body 'help' to > [email protected] > > You can reach the person managing the list at > [email protected] > > When replying, please edit your Subject line so it is more specific > than "Re: Contents of Planner-list digest..." > > > Today's Topics: > > 1. Re: New user and first feedback. (Alexandre Franke) > > > ---------------------------------------------------------------------- > > Message: 1 > Date: Mon, 8 Mar 2010 14:55:20 +0100 > From: Alexandre Franke <[email protected]> > To: [email protected] > Subject: Re: Planner-list New user and first feedback. > Message-ID: > <cf01fe061003080555l60231bcei11f1477aebdd104-JsoAwUIsXosN+BqQ9rBEUg@public.gmane.org> > Content-Type: text/plain; charset=UTF-8 > > On Sun, Mar 7, 2010 at 10:47 PM, Leonardo Perez <[email protected]> wrote: > > Hello. > > Hi, > > > I'm just using planner for Linux. I'm very glad to find this programme, > > using Planner, I'll never go back to Windows and MS Proyect. > > I'm Engieneer and I use MS Proyect constantly. I found that in MS Proyect, > > as in Planner, the cost of the Work Resources always it's rated with the > > hour's assignment, but, in some proyects You may to hire personal payed full > > time or part time, in this cases the costs are fixed. and the personal's > > budget too. > > > > I would like to find, as a option, to choose the kind of personal's payment, > > Fixed or rated by hours. > > Have a look at https://bugzilla.gnome.org/show_bug.cgi?id=138936 > > -- > Alexandre Franke > > > ------------------------------ > > _______________________________________________ > Planner-list mailing list > [email protected] > http://mail.gnome.org/mailman/listinfo/planner-list > > > End of Planner-list Digest, Vol 43, Issue 3 > ******************************************* _________________________________________________________________ Explore the seven wonders of the world http://search.msn.com/results.aspx?q=7+wonders+world&mkt=en-US&form=QBRE _______________________________________________ Planner-list mailing list [email protected] http://mail.gnome.org/mailman/listinfo/planner-list