Planner-list Task Completion in Planner
Charlie Warner <[email protected]> Sun, 21 Mar 2010 16:04:57 -0500
| Newsgroups | gmane.comp.gnome.apps.planner.user |
|---|---|
| Message-ID | <[email protected]> |
I am using Planner 0.14.13 in Ubuntu 9.10. I notice that I can not increase the task completion entry above 75%, although I can drag the completion bar to 100% in Gantt view (which does not change the Task details). I have searched the archives, and find that this same issue was addressed back in 2008, but I find nothing to indicate that a solution was finally advanced or a work-around developed. So, how does one get a task to show 100% complete? Charlie Warner _________________________________________________________________ Hotmail: Trusted email with Microsoft’s powerful SPAM protection. https://signup.live.com/signup.aspx?id=60969 _______________________________________________ Planner-list mailing list [email protected] http://mail.gnome.org/mailman/listinfo/planner-list