Planner-list Work units
Ken Smith <[email protected]>
| Newsgroups | gmane.comp.gnome.apps.planner.user |
|---|---|
| Organization | K-Net Technology |
| Message-ID | <[email protected]> |
Hi, First post this this list. Is it possible to have a work unit entry less than an hour, or fractions of an hour such as 0.5? I have seen that the units in the xml file are in seconds and manually changing an entry to 1800 appears to make a task last half an hour in the Gantt display. Is there a way to make that entry through planner rather than hacking the xml file? Thanks Ken -- This message has been scanned for viruses and dangerous content by MailScanner, and is believed to be clean.