Joachim Fehn <Joachim.Fehn-/ixSogHR0HOS/[email protected]>
Newsgroups gmane.comp.gnome.apps.planner.user
Organization fsc ip sw os 6
Message-ID <[email protected]>
Hi,

I'm planning a project with the great planner tool. But I'm confused by the 
way, resources are handled.

I defined resources, especially a team named OS6 (type work) and tasks. The 
tasks named Server and Authentication require the resource OS6 by 100% each. 
I mean, the two tasks should be one after the other, because the team can do 
only one job at a time: 1st Server (prio 8), then Athentication (prio 4).

planner puts the two tasks into the same time slice an produces a resource 
usage of 200%.

How can I get it working?

(planner 0.14.2 on openSuse 10.3)

BTW: Is there an online manual? I didn't find one with the distribution nor at 
gnome.org.

Thanx, Regards
  Joachim Fehn

-- 
Joachim Fehn                      Senior Expert Developer -- IP SW OS 6
Fujitsu Siemens Computers GmbH    www.fujitsu-siemens.de
Otto-Hahn-Ring 6                  www.fujitsu-siemens.de/imprint.html
D-81739 Muenchen                  Joachim.Fehn-/ixSogHR0HOS/[email protected]
lmpx.com only provides a reader for public news (NNTP) servers. It is not affiliated with the servers or forums shown here and is not responsible for the content of articles, which is written by their respective authors.