[openi18n-im:01383] Re: r12.4 and r12.2.1 schedule draft

Jens Petersen <[email protected]> Wed, 18 May 2005 15:49:17 +0900
Newsgroups gmane.comp.internationalization.input-methods
Message-ID <[email protected]>
Leon Ho wrote:
> r12.2.1
>   Code Freeze - Jun 21
>   QA Period - Jun 22-24
>   Release - Jun 28

So there should be an rc (12.2.0.9x) say Jun 21.

> r12.4
>   Feature Freeze - May 27
>   API/ABI Freeze - Jun 30
>     r12.3-beta1

How about July 15 for beta1

>     r12.3-beta2

and Aug 5 for the beta2?

All 12.3 releases are development releases anyway, so I would suggest naming the 
betas just 12.3.x.

>   Code Freeze - Aug 19
Implementation Freeze - Aug 12

Although the schedule is tight enough as it is, I was thinking it might be 
better to make an "Implementation Freeze" before the Code (devel) Freeze to give 
more time for release stabilisation and allow developers also to concentrate on 
bugfixing at the end of the cycle.

>     r12.3-rc1

Aug 19

>     r12.3-rc2

and Aug 26?

Again I'd prefer 12.3.9x for RC releases.

>   QA Period - Aug 22-26
>   Release - Aug 31

Does anyone know when the O'bon holiday is in Japan this year,
I hope it won't overlap too much with our release schedule?