[openi18n-im:01384] Re: r12.4 and r12.2.1 schedule draft
Lawrence Lim <[email protected]> Wed, 18 May 2005 17:29:34 +1000
| Newsgroups | gmane.comp.internationalization.input-methods |
|---|---|
| Message-ID | <[email protected]> |
Hi all,
I have updated the wiki after aligning myself with Jens. Here is my
proposal. I was contemplating whether to perform QA before or after beta
release and finally decided to go with after. If things does not turn
out well, I will then adjust accordingly.
r12.4
* Feature Freeze - May 27
* API/ABI Freeze - Jun 30
* r12.3-beta1 - Jul 15
* QA Period - Jul 18-20
* r12.3-beta2 - Aug 5
* QA Period - Aug 8-10
* Code Freeze - Aug 19
* r12.3-rc1 - Aug 19
* QA Period - Aug 22-23
* r12.3-rc2 - Aug 26
* QA Period - Aug 29-31
* Release - Aug 31
Thanks,
Lawrence
On Wed, 2005-05-18 at 16:49, Jens Petersen wrote:
> Leon Ho wrote:
> > r12.2.1
> > Code Freeze - Jun 21
> > QA Period - Jun 22-24
> > Release - Jun 28
>
> So there should be an rc (12.2.0.9x) say Jun 21.
>
> > r12.4
> > Feature Freeze - May 27
> > API/ABI Freeze - Jun 30
> > r12.3-beta1
>
> How about July 15 for beta1
>
> > r12.3-beta2
>
> and Aug 5 for the beta2?
>
> All 12.3 releases are development releases anyway, so I would suggest naming the
> betas just 12.3.x.
>
> > Code Freeze - Aug 19
> Implementation Freeze - Aug 12
>
> Although the schedule is tight enough as it is, I was thinking it might be
> better to make an "Implementation Freeze" before the Code (devel) Freeze to give
> more time for release stabilisation and allow developers also to concentrate on
> bugfixing at the end of the cycle.
>
> > r12.3-rc1
>
> Aug 19
>
> > r12.3-rc2
>
> and Aug 26?
>
> Again I'd prefer 12.3.9x for RC releases.
>
> > QA Period - Aug 22-26
> > Release - Aug 31
>
> Does anyone know when the O'bon holiday is in Japan this year,
> I hope it won't overlap too much with our release schedule?
>
> Jens