Re: resource exclusivity

Dag Andersen <[email protected]> Mon, 26 Nov 2007 15:16:36 +0100
Newsgroups gmane.comp.kde.kplato
Message-ID <[email protected]>
Fredag 23 november 2007 16:17 skrev Marco Correia:
> Hi,
>
> I have two tasks sharing the same resource (a programmer). Kplato does not
> seem to care about the regular work time of this programmer and just puts
> them in parallel, making the programmer work overtime.
Yep, this will be the state of afairs until the next major release (koffice 
2.0)
>
> How do I tell kplato to respect the amount of resources, that is, to find a
> schedule where no one works overtime, sliding the tasks to the right if
> needed?
You'll need to define some other constraint. Either dependencies or timing 
constraints. Not elegant in any way, but kplato is still 0.x version so the 
functionallity is limited.
>
> thanks
> Marco
> (please answer to this email, since I'm not subscribed to the mailing list)

-- 
Mvh
Dag Andersen