Re: resource exclusivity
Dag Andersen <[email protected]> Mon, 26 Nov 2007 15:16:36 +0100
| Newsgroups | gmane.comp.kde.kplato |
|---|---|
| Message-ID | <[email protected]> |
Fredag 23 november 2007 16:17 skrev Marco Correia: > Hi, > > I have two tasks sharing the same resource (a programmer). Kplato does not > seem to care about the regular work time of this programmer and just puts > them in parallel, making the programmer work overtime. Yep, this will be the state of afairs until the next major release (koffice 2.0) > > How do I tell kplato to respect the amount of resources, that is, to find a > schedule where no one works overtime, sliding the tasks to the right if > needed? You'll need to define some other constraint. Either dependencies or timing constraints. Not elegant in any way, but kplato is still 0.x version so the functionallity is limited. > > thanks > Marco > (please answer to this email, since I'm not subscribed to the mailing list) -- Mvh Dag Andersen