Prompt for Overwrite does not work in VS.NET Integration

"Chris Mullins" <[email protected]> Tue, 2 Mar 2004 21:26:37 -0800
Newsgroups gmane.comp.version-control.sourcegear-vault.user
Message-ID <[email protected]>
Open a project in Source Control

 

Make a bunch of changes.

 

Right-Click on the Solution, and (by mistake) click "GetLatest" instead
of "Check In". Think for a moment "Do I kill the process or let it
finish?". 

 

All checked-out files are overwritten. 

 

 "Prompt on Overwrite" is enabled in the Vault GUI. 

 

-- 