Milestone Update
"Menachem Dodge" <[email protected]> Thu, 29 Nov 2007 14:27:07 +0200
| Newsgroups | gmane.ietf.adslmib |
|---|---|
| Message-ID | <[email protected]> |
Hi,
The milestones need to be updated to reflect the actual progress of the
documents.
I propose the following milestones:
For the G.Bond documents:
Dec 2007 - Complete the work on all the four G.Bond documents.
Jan 2007 - Working Group Last Call on all the G. Bond documents.
Feb 2007 - Early MIB Doctor Review of all G.Bond documents.
March 2008 - Make Corrections to the G.Bond drafts following the review.
April 2008 - Working Group Last Call for G.Bond documents following
corrections.
May 2008 - Present the four G. Bond documents to the IESG.
For the Vdsl2 document:
Dec 2007 - Post Vdsl2 draft version 04.
Jan 2008 - Complete Thorough Working Group Reviews of the Vdsl2 draft
and produce version 05.
Feb 2008 - Working Group Last Call for the Vdsl2 document.
March 2008 - Early MIB Doctor Reviews of the Vdsl2 draft.
April 2008 - Make Correction to the draft following the review.
May 2008 - Working Group Last Call for the Vdsl2 document following
corrections.
June 2008 - Present the Vdsl2 document to the IESG.
Comments?
Best Regards,
Menachem