Re: Milestone Update

Scott Baillie <[email protected]> Fri, 30 Nov 2007 10:03:18 +1100
Newsgroups gmane.ietf.adslmib
Organization NEC Australia
Message-ID <[email protected]>
Hi Menachem,

The schedule for VDSL2 sounds reasonable to me.

Regards,

Scott.

On Thu, 2007-11-29 at 14:27 +0200, Menachem Dodge wrote:
> Hi,
>     
>  
> The milestones need to be updated to reflect the actual progress of
> the documents. 
>  
> I propose the following milestones:
>  
>  For the G.Bond documents:
> Dec 2007 - Complete the work on all the four G.Bond documents. 
> 
> Jan 2007 -  Working Group Last Call on all the G. Bond documents. 
> 
> Feb 2007 - Early MIB Doctor Review of all G.Bond documents. 
> 
> March 2008 - Make Corrections to the G.Bond drafts following the
> review.
> 
> April 2008 - Working Group Last Call for G.Bond documents following
> corrections. 
> 
> May 2008 - Present the four G. Bond documents to the IESG. 
> 
>  
> 
>  
> 
> For the Vdsl2 document:
> 
> Dec 2007 - Post Vdsl2 draft version 04. 
> 
> Jan 2008 - Complete Thorough Working Group Reviews of the Vdsl2 draft
> and produce version 05. 
> 
> Feb 2008 - Working Group Last Call for the Vdsl2 document.
> 
> March 2008 - Early MIB Doctor Reviews of the Vdsl2 draft.
> 
> April 2008 - Make Correction to the draft following the review. 
> 
> May 2008 - Working Group Last Call for the Vdsl2 document following
> corrections.
> 
> June 2008 - Present the Vdsl2 document to the IESG.
> 
>  
> 
> Comments?
> 
> 
> Best Regards,
> Menachem
>  