Milestones Update
Margaret Wasserman <[email protected]>
| Newsgroups | gmane.ietf.entmib |
|---|---|
| Message-ID | <[email protected]> |
Hi All,
Based on our discussion in Atlanta, we need to change our
milestones, in order to reflect that the state/status
extensions to the Entity MIB will be published as a separate
document.
I don't know whether this requires a charter text update, or
just a milestone update. Bert, do you have any thoughts?
I propose the following milestone changes:
OLD:
DEC 02 Re-cycle the updated Entity MIB at proposed standard, if necessary
MAR 03 Evaluate status of the Entity MIB and collect implementation and
interoperability reports
MAR 03 Evaluate status of the Sensor Entity MIB and collect
implementation and
interoperability reports
MAY 03 Recommend to the IESG if the Entity MIB can be elevated to Draft
Standard.
MAY 03 Recommend to the IESG if the Sensor Entity MIB can be elevated to
Draft Standard
JUN 03 Re-charter or shut-down the WG
NEW:
DEC 02 Publish state/status extensions as a WG I-D
FEB 03 Submit state/status extensions to the IESG for Proposed Standard
MAR 03 Evaluate status of the Entity MIB and collect implementation and
interoperability reports
MAR 03 Evaluate status of the Sensor Entity MIB and collect
implementation and
interoperability reports
MAY 03 Submit the Entity MIB to the IESG for Draft Standard.
MAY 03 Submit the Sensor Entity MIB to the IESG for Draft Standard
JUN 03 Re-charter or shut-down the WG
Sharon, I'd particularly like to know if you are comfortable
with these dates for the state/status work.
Thanks,
Margaret