RE: Data Center Facility Costs

"Kevin Kargel" <kkargel-BvA0c2rBOuxWk0Htik3J/[email protected]>
Newsgroups gmane.org.operators.internet-access
Message-ID <70DE64CEFD6E9A4EB7FAF3A0631410660104F436@mail>
That's one reason I am rather surprised that some server farm hasn't
moved in here.  There is good power available, cheap real estate,
existing empty structures, a friendly economic development committee,
easy bandwidth close to the backbone, a modern school and brand new
hospital.  We may not have stop lights (a traffic jam is three cars at
the same intersection) but we do have a grocery store, hardware store
and movie theatre. We even have a very nice coffee shop and a hotel.  I
work at the telco/ISP and we are a co-op, which lets us be less
structured than the big boys and do more custom installations for our
customers.  

I love living in a rural environment with a tech job, the best of both
worlds in my opinion.  I get to play with routers and Internet all day,
and at 4:30 jump in the car and I'm 5 minutes away from great hunting
and fishing grounds.  

Perhaps the only lacking resource would be a workforce, but you should
be able to import that, and the on site workforce for a server farm
really doesn't need to be that extensive.  just a few guys to do the
touchy-feeley stuff..

I am not recruiting here..  more like bragging..  :) ... but having said
that I would be willing to act as a point of contact to put you in touch
with city government.  



> -----Original Message-----
> From: [email protected] 
> [mailto:[email protected]] On Behalf Of Alex Rubenstein
> Sent: Friday, March 07, 2008 9:19 AM
> To: [email protected]
> Subject: RE: Data Center Facility Costs
> 
> ... and have no fiber.
> 
> That is the hard part, finding the intersection of lots of 
> fiber, cheap power, power availability***, labor resource, 
> real estate, and customers.
> 
> 
> *** Never, ever make an assumption that because you need 
> power that the utility can (or will) provide it. In fact, 
> things are so constrained in NJ that we have to pay them to 
> do power studies to see if loads even as small as 3 or 4 
> megawatts won't break them. Then, they want us to pay 
> reservation fees.
> 
> 
> > You guys got me curious, so I called and checked..  here in Park 
> > River, ND , the small installation charge for power is .074/kwh 
> > (either 1 phase or 3 phase), and for large installations (I am 
> > guessing that means big enough to get your own transformer, or over 
> > 200 Amps, or something) the cost is .0645/kwh .
> > 
> > Of course the main advantage here is that real estate is 
> cheap enough 
> > that you can buy a building with your mastercard..  lol..
> 
> --
> Eat sushi frequently. - Avi
> [email protected] is the human contact address.
> [email protected] is the list posting address.
> See below URL for subscribe/unsubscribe and list options:
> http://inet-access.net/mailman/listinfo/list
> 
-- 
Eat sushi frequently. - Avi
[email protected] is the human contact address.
[email protected] is the list posting address.
See below URL for subscribe/unsubscribe and list options:
http://inet-access.net/mailman/listinfo/list
lmpx.com only provides a reader for public news (NNTP) servers. It is not affiliated with the servers or forums shown here and is not responsible for the content of articles, which is written by their respective authors.