Re: Any news?

Richard Hult <[email protected]> 22 Apr 2003 13:51:15 +0200
Newsgroups gmane.comp.gnome.apps.mr-project.devel
Organization CodeFactory AB
Message-ID <[email protected]>
l=F6r 2003-04-19 klockan 18.29 skrev Benjamin BAYART:

> I got a look at the drag'n'drop stuff and found a funny behaviour of the
> current Gantt Chart/Row on that point: What is changed by the
> drag-duration is not the duration, but the work, which have strange
> effect.
>=20
> Suppose a task that have a duration of 2 days, and a work of 4 days, and
> a resource assigned to it, the resource is assigned at 200%. When you
> drag it's duration, and change your mind, get back to 2 days, and
> release the button, the *work* is set to 2 days, and so the duration is
> half what you expected graphically.
>=20
> In my guess, what you *see* on the chart is a duration, not a work...
> Should this considered a bug? Is it already in bugzilla? Should I fill
> it? What behaviour should I adopt for the same functionality in my view?

It's a bug. What you see in the gantt chart is the duration, and when
you drag a bar, it should set the work required to achieve the specified
duration. Somehow, this is messed up right now when having an assignment
other than 100%.

Also, I guess we should set the duration instead of work for tasks that
use fixed duration mode.

I just added two bugs reports to the bugzilla about this (#638, #639).

Regards,
Richard=20

--=20
Richard Hult                    [email protected]
CodeFactory AB                  http://www.codefactory.se/