Re: Planner-list there is no way to move task in time off ?

Gabriel Rota <[email protected]> Fri, 19 Feb 2010 13:02:30 +0100
Newsgroups gmane.comp.gnome.apps.planner.user
Message-ID <1266580950.24159.60.camel@grota-laptop>
Il giorno ven, 19/02/2010 alle 11.34 +0100, Mariusz Pekala ha scritto:
> I suppose you need to use menu: "Project->Edit Day Types" and add a new
> day type. The hard part will be to choose a name for this type ;-).
> Let's call it 'Maintenance' or 'Working and Maintenance' or 'Working
> late'.
> 
> Then go to "Project->Manage Calendars", select the calendar in the left
> column (if you have created more calendars).
> Click the button [Working time...], select the just-created-day-type,
> type the hours (8:00 - 17:00 / 18:30 - 19:30, for example) and click
> [Apply], then [Close].
> 
> Select the day you want to change (February 19, for example) and near
> the bottom you will see an option 'Set day type to:'.
> Choose the just-created-day-type and click [Apply].
> 
> I hope this helps. :)

Excellent!

This tool is wonderful:)
and the problem is my little in-depth knowledge
next time my coworker use planner for this work:)
through the excellent explanation, joining yours and Alexandre I can
make all I want:)

thanks all two

_______________________________________________
Planner-list mailing list
[email protected]
http://mail.gnome.org/mailman/listinfo/planner-list
signature.asc (application/pgp-signature, 197 B)
-----BEGIN PGP SIGNATURE-----
Version: GnuPG v1.4.9 (GNU/Linux)

iEYEABECAAYFAkt+fdYACgkQ6170uvayTYxTuACg2TM8mGVTbtadgwKMGd10WHml
vbkAn2nNOXIgzXa2Uk5XLNL6dQSW3bdV
=V6G4
-----END PGP SIGNATURE-----