MRP Time Fence.

"Jim Kerr" <JKerr-FaIC0pVkSM6w7v2zf2itdNJR4SXAr38/@public.gmane.org>
Newsgroups gmane.comp.systems.as400.jbausers
Organization Gleason Corporation
Message-ID <000a01c857dc$3a822b10$3201a8c0@DBQ2M441>
On the MRP Inquiry summary screen (MR050), there are 4 dates displayed at
the top of the screen;

 

Start 5/11/07   Time Fence  6/26/09   F/C Time Fence 1/16/08    End  6/26/09

 

I am interested in knowing what creates the value for the "Time Fence"  and
"End"   dates. These fields appear to be taken from file MSP71, fields
PSTF71  and PSED71 respectively. I also note that there is a value in field
LTIW71 (Purchasing lead time) of 420, does this get used in calculating the
time fence and end date and if so, where is that value coming from ? 

 

TIA,

 

Jim. 

 

_______________________________________________
This is the System 21 Users (SYSTEM21) mailing list
To post a message email: SYSTEM21-Zwy7GipZuJhWk0Htik3J/[email protected]
To subscribe, unsubscribe, or change list options,
visit: http://lists.midrange.com/mailman/listinfo/system21
or email: SYSTEM21-request-Zwy7GipZuJhWk0Htik3J/[email protected]
Before posting, please take a moment to review the archives
at http://archive.midrange.com/system21.
lmpx.com only provides a reader for public news (NNTP) servers. It is not affiliated with the servers or forums shown here and is not responsible for the content of articles, which is written by their respective authors.