Orville, 

I did this for a prior employer - not integrating AutoRelease, but a daily 
scheduling application that I used to simulate an advanced planning solution (I 
didn't have the budget to acquire AVP).  How I did it was to take the output 
from the daily scheduling application, clear all firm planned orders from MPSP 
for the planner designated for the end items, and programmatically create firm 
planned orders for each day's scheduled production.  This was done immediately 
prior to our weekly (or more frequent as required) MPSP/MRP process.

Since we generally built to a planned overall schedule for a total number of 
units, this worked well for us.  It wasn't an ideal solution, but was quite 
effective for us while we were producing that product line.  It basically gave 
us the benefit of maintaining a somewhat flexible daily production schedule and 
also gave us the benefits of planning all components in MRP (we produced between 
80-90% of the components in house).  In other words, we integrated a demand 
planning process at the top end, with a batch ordering process at the lower 
levels.

It actually wasn't that difficult to do.  However, having said that, it only 
worked for us because we were able to maintain a steady level of production at 
the top level/end item level, and there was a fairly high percentage of common 
components for that product.  


I had intended to extend that process to other areas of the company, but the 
company decided to abandon that product line before I was able to do so.

 Dale (Cork) Gindlesperger, CPIM 






________________________________
From: "[email protected]" <[email protected]>
To: mapics-l-Zwy7GipZuJhWk0Htik3J/[email protected]
Sent: Mon, October 25, 2010 3:31:07 PM
Subject: [MAPICS-L] Need help with MRP


Hello,

I have two Infor packages.  One is AutoRelease (for EDI) and the other is
XA 7.7.  What I am trying to do is split the weekly (from AutoRelease)
buckets into daily buckets in MRP.  Looked through the manuals and they
were not any help.

Has someone else been able to do this within XA?



Orville Meredith
Systems Analyst

Gecom Corporation
1025 Barachel Lane
Greensburg, IN  47240

[email protected]

812-663-1745 (T)
812-663-2230 (F)

812-718-9028 (C)
(Travel, after 4:00 p.m. weekdays, and weekends ONLY)

== This message has been scanned for viruses ==
_______________________________________________
This is the MAPICS ERP System Discussion (MAPICS-L) mailing list
To post a message email: MAPICS-L-Zwy7GipZuJhWk0Htik3J/[email protected]
To subscribe, unsubscribe, or change list options,
visit: http://lists.midrange.com/mailman/listinfo/mapics-l
or email: MAPICS-L-request-Zwy7GipZuJhWk0Htik3J/[email protected]
Before posting, please take a moment to review the archives
at http://archive.midrange.com/mapics-l.


      
_______________________________________________
This is the MAPICS ERP System Discussion (MAPICS-L) mailing list
To post a message email: MAPICS-L-Zwy7GipZuJhWk0Htik3J/[email protected]
To subscribe, unsubscribe, or change list options,
visit: http://lists.midrange.com/mailman/listinfo/mapics-l
or email: MAPICS-L-request-Zwy7GipZuJhWk0Htik3J/[email protected]
Before posting, please take a moment to review the archives
at http://archive.midrange.com/mapics-l.
lmpx.com only provides a reader for public news (NNTP) servers. It is not affiliated with the servers or forums shown here and is not responsible for the content of articles, which is written by their respective authors.